Colac's Ambulance Station was relocated to a new site in Rae St on
the 12 November 2003 due to Colac's Hospital redevelopment.
Below is the progressive development of the new station.

         
 
 
Week 1

16 June 2003

Block of land purchased and fenced off in preparation of construction.

Click here for more pictures

 

   
 
 
Week 2

23 June 2003

Site Office and building in place.

Ambulance Station foundations pegged out.

Click here for more pictures

   
 
 
Week 3

30 June 2003

Boundary fencing in place.

Garage framework up.

Foundations for station slab dug.

Click here for more pictures

   
 
 
Week 4

7 July 2003

Nil progress.

 

   
 
 
Week 5

14 July 2003

Slab laid for station house.

Garage framework up.

Click here for more pictures

   
 
 
Week 6

21 July 2003

Framework for station house walls being erected.

Garage roofing in place.

Click here for more pictures

   
 
 
Week 7

28 July 2003

Framework for station house walls completed.

Click here for more pictures

   
   
 
 
Week 8

4 August 2003

Station house roof frame now complete.

Click here for more pictures

   
 
 
Week 9

11 August 2003

Station house wall insulation wrapping in place.

Click here for more pictures

   
   
 
 
Week 10

18 August 2003

Station house roof iron half completed.

Brickwork completed below floor line.

Click here for more pictures

   
 
 
Week 11

25 August 2003

Station roof almost complete.

External windows & doors in place.

Internal electrical wiring begun.

Click here for more pictures

   
 
 
Week 12

01 September2003

Garage concrete slab now laid.

Some brickwork around station office now complete.

Click here for more pictures

   
 
 
Week 13

08 September 2003

External brickwork around building now complete.

Internal electrical wiring laid throughout the building, awaiting plastering to finish.

Work on storm water drainage begun.

Click here for more pictures

   
 
 
Week 14

15 September 2003

Storm water drainage now complete.

Internal plastering begun in wet areas.

Click here for more pictures

   
 
 
Week 15

22 September 2003

Internal plastering & electrical work continues.

Preparation for driveway concreting begins.

Click here for more pictures

   
 
 
Week 16

29 September 2003

Internal plastering & electrical work continues.

All cupboards and kitchen throughout building in place.

Garage cladding begins.

Click here for more pictures

   
 
 
Week 17

6 October 2003

Internal plastering & electrical work continues.

Concreting of driveway now complete.

Click here for more pictures

   
 
 
 
Week 18

13 October 2003

Painting of branch almost complete.

Garage cladding completed.

Click here for more pictures

 
 
Week 19

20 October 2003

Painting now complete.

Floor coverings started

Landscaping begun.

Click here for more pictures

 
 
 
Week 20

27 October 2003

Radio tower & wiring completed.

Landscaping now finished.

Folding doors in place.

Click here for more pictures

 
 
 
Week 21

3 November 2003

Final week - Handover 10 November.

Final finishing and cleanup underway.

Click here for more pictures

 

 

 

Week 22

12 November 2003

First rostered shift in the new station.

Click Here for more pictures

 
 
 